Marco Polo
Project Gallery
Bob Coes sends us
this update showing the placement of the deck houses on the main deck on
September 17/08. Gary Allport, Operations Manager at Logistec West Side
Terminal, was kind enough to offer the services of their men and equipment.
Equipment operators Wayne Brown and Mike Cochrane lifted the deck houses into
position with one of Forterm's heavy duty forklifts. Special thanks to Logistec
for helping us out. The following photos describe the overall loading process.
Bob Coes Project Manager
We still need lots
of support to keep this project moving ahead, if you'd like to help us out with
a donation please contact Barry Ogden at 849-4650.
September
24/2008 Just click on the pics for
larger view.
 |
 |
 |
| The
first three photos show the Forterm forklift with fork extensions installed for
lifting the deck houses. The forward deck house was lifted first. |
 |
 |
| Driver is Wayne
Brown with co-worker Mike Cochrane. |
Forward deck
house is set down to load on starboard side. |
 |
 |
| Loading forward deck house on starboard side. |
 |
 |
 |
 |
 |
| 5
photos above taken of the loading of the aft deck house on the starboard side.
|
 |
 |
| Left to right:
Larry Cosman, Wayne MacEachern, Lino Celeste, Ken Sparks. Deck houses moved
over opening. |
Stbd side showing
deck houses in position. Stanchions will be installed on stbd side next. Due to
height restrictions in the lifting process the stanchions were left off so as
to allow for the space needed to carry out the lift. |
 |
 |
| Shot of port
side. Stanchions already in place. |
Port Quarter.
Deck houses will be scribed and fitted to the main deck. Their elevation will
be lowered by approximately one foot. |